June 2019 Quarterly Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
Date: 30 July 2019
No. 628/30072019
Market Cap
JUNE 2019 QUARTERLY REPORT
A$9.2 m (0.007 p/s)
1. BLACK RIDGE GOLD PROJECT, QLD (IPT 100%, option to buy 95%)
Increasing focus on potential gold production opportunity at Black
Ridge on granted mining lease and 4 mining lease applications.
Purchase and commissioning of 50 tonne per day mobile wet
processing plant.
Second phase of bulk sampling completed. Assays awaited.
Successful performance of the wet processing plant confirms
potential for large volumes of free-digging, easily processable oxide
ore on the mining leases.
Issued Capital
1,321,679,789
Listed Options
499,910,556
IPTOA
2. COMMONWEALTH PROJECT (IPT 100%)
Resource update for Commonwealth and Silica Hill underway
3. CORPORATE
Cash at June 30th: $2.0 million.
Sold share holding in Pacton Gold Inc. for net proceeds of $423,000.
Directors
Peter Unsworth
Chairman
Dr Michael Jones
Managing Director
Paul Ingram
Non-Executive Director
Markus Elsasser
Non-Executive Director
Eamon Hannon
Non-Executive Director
Bernard Crawford
Company Secretary
a 26 Richardson Street
West Perth
Western Australia 6005
t +61 (8) 6454 6666
f +61 (8) 6314 6670
e info@impactminerals.com.au
www.impactminerals.com.au
1. BLACKRIDGE GOLD PROJECT (IPT100% and option for 95%)
During the Quarter Impact increased its focus on its advanced Black Ridge gold project located about
20 km north of Clermont in central Queensland (Figure 1). Here, as part of the overall land holding,
Impact owns a granted mining lease and has under option-to-purchase four other mining lease
applications, all of which have the potential for near term gold production subject to on-going
positive exploration results.
Figure 1. Location and regional geology of the Black Ridge gold project. The project lies at the
southern end of the Miclere-Black Ridge Basin, the northern-most of a series of Permian
intracratonic sedimentary basins that are also host to major coal deposits.
Impact has shown that previous exploration drilling at Black Ridge may have underestimated the
grade at the project because of a potentially significant “nugget effect” (ASX Release May 29th 2018).
Accordingly large bulk samples were judged to be the most cost effective exploration method for
such a nuggety style of gold mineralisation and two phases of sampling, Phase 1 and Phase 2, have
now been completed.
The Phase 1 work, in which each bulk sample weighed about 1 tonne, demonstrated that the project
area potentially contains large volumes of free-digging, gold-mineralised oxide material (weathered
rock) that was easily processed using simple water-based gravity separation equipment (ASX Release
October 3rd 2018).
The aim of the Phase 2 work was to help determine if the wet processing of about 10 times more
volume of oxide material was possible and determine the potential for even larger samples or trial
mining to be undertaken in a future third Phase of work.
Accordingly in order to expedite the results of the Phase 2 programme, a second-hand small mobile
water processing plant capable of processing up to 50 tonnes of material per day was purchased by
Impact (Figure 3).
The plant was commissioned using the 3 samples that were not processed from the Phase 1 bulk
sample programme because of their high clay content (ASX Release October 3rd 2018). These 3
samples have been sent for assay together with the samples from the Phase 2 programme.
Figure 2. Commissioning of Mobile Wet Processing Plant for Gold
Phase 2 Bulk Sampling Programme
A total of 14 bulk samples were taken in Phase 2 for about 160 tonnes of material, mostly on the
company’s 100% owned granted Mining Lease ML2386. The water processing plant performed
exceptionally well with the free digging oxide material separating easily in the trommel and sluice.
Figure 3. Impact’s water processing set up for the bulk samples at Black Ridge.
Panned concentrates from the bulk samples have been sent for assay with results expected shortly.
In addition the fine “overflow” material from the processing plant and panning process has also been
assayed to determine the efficacy of the plant in retrieving fine gold.
The strike potential at the high grade Foxes Lead (or “run”) on ML2386 was tested by taking 50m
spaced bulk samples over about 300 metres of strike along the target unconformity to assess the
grade distribution and determine the potential for any further high grade “runs” (Figure 4). A
compilation of previous production data from Government records indicated the grade within these
runs was commonly more than one ounce per tonne (Figure 4 and ASX Release October 3rd 2018).
In addition samples were taken in trenches at the Harveys and Smiths prospects (Figure 4) which
previously returned high grade results of up to 592 g/m3 (approximately 297 g/t) from much smaller
samples (ASX Release October 3rd 2018). There is significant potential at these two prospects to
define a previously undiscovered high grade “run” at surface within the target conglomerate unit.
The results of this work will be used as a basis to determine if an Exploration Target can be calculated
for the gold mineralisation at Black Ridge. This would underpin internal economic studies to make a
decision on the nature of the next stage of work at the project.
ABOUT THE BLACK RIDGE PROJECT
Impact’s project covers 91 square kilometres and comprises one 100% owned granted mining lease
(ML2386), one 100% Exploration Permit (EPM26806) and and option to purchase 95% of a further
Exploration Permit (E26066) and four Mining Lease applications (ML 100158, 59, 60 and 61) from
Rock Solid Holdings Pty Limited (Figures 4 and 5; ASX Release May 29th 2018).
The project covers the historic Black Ridge and Springs mining centres which together with other
areas around Clermont produced about 185,000 ounces of gold from 1879 to the early 1900’s from
surface down to depths of about 70 metres in small shafts and related underground workings.
Further discoveries were made in the Clermont area in the 1930’s and total production from the area
is estimated by the Geological Survey of Queensland to be more than 300,000 ounces of gold (ASX
Release May 29th 2018).
Figure 4. Gold production data and Phase 1 bulk sample results at Black Ridge.
The gold produced at Black Ridge was mostly hosted in basal conglomerates of Permian-aged
sedimentary basins which include the mined coal measures that unconformably overlie the Anakie
metamorphic rocks of Middle Ordovician age and older (Figures 4 and 5).
Figure 5. Tenure and geology of the Black Ridge gold project.
The unconformity is present at surface over about 1,500 metres of trend at Black Ridge. Much of the
lease is covered by loose gravel with only a few outcrops of conglomerate and schist in places. This
cover, within which small gold nuggets have been found by prospectors over many years, has
hindered previous exploration and there has been no recent systematic exploration in the area.
Previous bulk samples of about 1 tonne demonstrated that gold was widely distributed along the
exposed conglomerate unit and related colluvium. Of 12 samples taken of the main unit 11 returned
values of between 0.04 g/m3 to 2.2 g/m3 with one high grade result of 56 g/t from a 70 kg sample
along the unconformity (ASX Release 23rd October 2018). These results are encouraging for the
potential for bulk mining.
In addition the Compensation Agreement with the local landowner for ML2386 was also completed
during the Quarter.
Further progress was also made on the advancement of the four mining lease applications towards
grant and the associated compensation agreements with the land owners.
At present there are statutory limitations on the sample size that can be taken on all licences except
for ML2386. Once all the mining leases are granted, nearly two kilometres of strike of the target unit
will be available for bulk sampling and/or trial mining.
2. COMMONWEALTH PROJECT
During the Quarter resource consultants Optiro undertook a revised resource estimate for the
Commonwealth area and a maiden resource for the Silica Hill area, located on Impact’s 100%
owned Commonwealth Project in the Lachlan Fold Belt, New South Wales.
This work is being finalised.
3. CORPORATE
Cash at June 30th was $2.0 million.
Sale of Shares in Pacton Gold Inc.
During the Quarter Impact completed the sale of all of its shares in Pacton Gold Inc. for total net
proceeds of $423,000. The shares were part of the sale of Impact’s Pilbara gold holdings as
announced to the ASX on May 29th 2018. Impact received a total of $764,000 in cash and shares for
the sale.
Dr Michael G Jones
Managing Director
Competent Persons Statement
Exploration Results
The review of exploration activities and results contained in this report is based on information compiled by Dr Mike Jones, a Member of the Australian
Institute of Geoscientists. He is a director of the company and works for Impact Minerals Limited. He has sufficient experience which is relevant to the
style of mineralisation and types of deposits under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined
in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code). Dr Jones has
consented to the inclusion in the report of the matters based on his information in the form and context in which it appears.
Impact Minerals confirms that it is not aware of any new information or data that materially affects the information included in the previous market
announcements referred to and in the case of mineral resource estimates, that all material assumptions and technical parameters underpinning the
estimates continue to apply and have not materially changed.
Forward Looking Statements
This document may contain certain forward-looking statements. Forward-looking statements include, but are not limited to statements concerning Impact
Minerals Limited’s (Impact’s) current expectations, estimates and projections about the industry in which Impact operates, and beliefs and assumptions
regarding Impact’s future performance. When used in this document, words such as “anticipates”, “could”, “plans”, “estimates”,”seeks”, “intends”,
“may”, “potential”, “should” and similar expressions are forward-looking statements. Although Impact believes that its expectations reflected in these
forward-looking statements are reasonable, such statements are subject to known and unknown risks, uncertainties and other factors, some of which are
beyond the control of Impact and no assurance can be given that actual results will be consistent with these forward-looking statements.
Actual values, results or events may be materially different to those expressed or implied in this document. Given these uncertainties, recipients are
cautioned not to place reliance on forward-looking statements. Any forward-looking statements in this document speak only at the date of issue of this
document. Subject to any continuing obligations under applicable law and the ASX Listing Rules, Impact does not undertake any obligation to update or
revise any information or any of the forward-looking statements in this documnent or any changes in events, conditions or circumstances on which any
such forward-looking statement is based.
Tenement Information in accordance with Listing Rule 5.3.3
Status
IPT Interest at start of
quarter
IPT Interest at end of
quarter
EL5874
Granted
100%
100%
EL8212
Granted
100%
100%
EL8252
Granted
100%
100%
EL8504
Granted
100%
100%
EL8505
Granted
100%
100%
EL8632
Granted
100%
100%
EL7390
Granted
100%
100%
EL8234
Granted
100%
100%
EL8636
Granted
100%
100%
EL8674
Granted
100%
100%
EL8609
Granted
100%
100%
E39/988
Granted
100%
100%
E39/1072
Granted
100%
100%
E39/1439
Granted
100%
100%
E39/1441
Granted
100%
100%
E39/1513
Granted
100%
100%
E39/1761
Granted
100%
100%
E39/1766
Granted
100%
100%
E39/1767
Granted
100%
100%
E39/1997
Granted
100%
100%
E39/2018
Granted
100%
100%
E39/2019
Granted
100%
100%
E39/2065
Granted
100%
100%
Granted
100%
100%
EPM26806
Granted
100%
100%
ML2386
Granted
100%
100%
Project / Tenement ID
Commonwealth, NSW
Broken Hill, NSW
Mulga Tank,WA
Clermont, Qld
EPM14116
Black Ridge, Qld
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
+Rule 5.5
Appendix 5B
Mining exploration entity and oil and gas exploration entity
quarterly report
Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/13, 01/09/16
Name of entity
IMPACT MINERALS LIMITED
Quarter ended (“current quarter”)
ABN
52 119 062 261
30 JUNE 2019
Current quarter
$A’000
Year to date
(12 months)
$A’000
(271)
(2,583)
(b) development
-
-
(c) production
-
-
(d) staff costs
(63)
(314)
(e) administration and corporate costs
(128)
(714)
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
(a) exploration & evaluation
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
7
47
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Research and development refunds
712
1,357
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating
activities
257
(2,207)
2.
Cash flows from investing activities
2.1
Payments to acquire:
(11)
(93)
(b) tenements (see item 10)
-
-
(c) investments
-
-
(d) other non-current assets
-
-
(a) property, plant and equipment
+ See chapter 19 for defined terms
1 September 2016
Page 1
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Current quarter
$A’000
Year to date
(12 months)
$A’000
(a) property, plant and equipment
-
-
(b) tenements (see item 10)
-
341
(c) investments
423
423
(d) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
25
2.6
Net cash from / (used in) investing
activities
412
696
3.
Cash flows from financing activities
3.1
Proceeds from issues of shares
-
-
3.2
Proceeds from issue of convertible notes
-
-
3.3
Proceeds from exercise of share options
-
-
3.4
Transaction costs related to issues of
shares, convertible notes or options
-
-
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
-
-
3.10
Net cash from / (used in) financing
activities
-
-
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
1,334
3,514
Consolidated statement of cash flows
2.2
Proceeds from the disposal of:
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
257
(2,207)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
412
696
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
-
-
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
2,003
2,003
+ See chapter 19 for defined terms
1 September 2016
Page 2
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
503
334
5.2
Call deposits
1,500
1,000
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
2,003
1,334
6.
Payments to directors of the entity and their associates
Current quarter
$A'000
6.1
Aggregate amount of payments to these parties included in item 1.2
93
6.2
Aggregate amount of cash flow from loans to these parties included
in item 2.3
-
6.3
Include below any explanation necessary to understand the transactions included in
items 6.1 and 6.2
Directors’ fees, salary payments and superannuation.
Current quarter
$A'000
7.
Payments to related entities of the entity and their
associates
7.1
Aggregate amount of payments to these parties included in item 1.2
-
7.2
Aggregate amount of cash flow from loans to these parties included
in item 2.3
-
7.3
Include below any explanation necessary to understand the transactions included in
items 7.1 and 7.2
+ See chapter 19 for defined terms
1 September 2016
Page 3
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
8.
Financing facilities available
Add notes as necessary for an
understanding of the position
Total facility amount
at quarter end
$A’000
Amount drawn at
quarter end
$A’000
8.1
Loan facilities
-
-
8.2
Credit standby arrangements
-
-
8.3
Other (please specify)
-
-
8.4
Include below a description of each facility above, including the lender, interest rate and
whether it is secured or unsecured. If any additional facilities have been entered into or are
proposed to be entered into after quarter end, include details of those facilities as well.
9.
Estimated cash outflows for next quarter
9.1
Exploration and evaluation
300
9.2
Development
-
9.3
Production
-
9.4
Staff costs
80
9.5
Administration and corporate costs
120
9.6
Other (provide details if material)
9.7
Total estimated cash outflows
10.
Changes in
tenements
(items 2.1(b) and
2.2(b) above)
10.1
Interests in mining
tenements and
petroleum tenements
lapsed, relinquished
or reduced
-
10.2
Interests in mining
tenements and
petroleum tenements
acquired or increased
-
+ See chapter 19 for defined terms
1 September 2016
Tenement
reference and
location
$A’000
500
Nature of
interest
Interest at
beginning
of quarter
Interest
at end of
quarter
-
-
-
-
-
-
Page 4
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Sign here:
............................................................
(Director/Company Secretary)
Print name:
Bernard Crawford
Date: 30 July 2019
Notes
1.
The quarterly report provides a basis for informing the market how the entity’s activities have
been financed for the past quarter and the effect on its cash position. An entity that wishes to
disclose additional information is encouraged to do so, in a note or notes included in or attached
to this report.
2.
If this quarterly report has been prepared in accordance with Australian Accounting Standards,
the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral
Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly report
has been prepared in accordance with other accounting standards agreed by ASX pursuant to
Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows
from investing activities, depending on the accounting policy of the entity.
+ See chapter 19 for defined terms
1 September 2016
Page 5
Share your feedback