LAKE HOPE SCOPING STUDY
Outstanding Economics show Lake Hope to potentially be the lowest-cost
producer of High Purity Alumina (HPA) globally by up to 50%
Impact Minerals Limited (ASX:IPT) is pleased to announce the positive results of a Scoping Study
based on realistic production and capital expenditure estimates for the company’s Lake Hope High
Purity Alumina (HPA) Project, located 500 km southeast of Perth in the Tier 1 jurisdiction of Western
Australia.
Cautionary Statement
The Lake Hope HPA Project Scoping Study in this ASX announcement was completed to assess the
potential economic viability of mining lake clays at Lake Hope with offsite metallurgical processing at
a plant near Kalgoorlie in Western Australia. The Scoping Study has been prepared to an accuracy
level of +/-30% and is a precursor to an ongoing Preliminary Feasibility Study (PFS). The results should
not be considered a profit forecast or production forecast.
The Scoping Study is a preliminary technical and economic study of the potential viability of the Lake
Hope project in accordance with the JORC Code 2012 and ASX Listing Rules. Impact advises that it is
based on low-level technical and financial assessments that will require a review to support an
estimate of Ore Reserves. Further evaluation work, including extensive metallurgical test work and
market acceptance studies of the final product, is required before an Ore Reserve can be estimated or
to provide any assurance of an economic development case.
The Study is based only on Indicated Resources announced to the ASX on 19th June 2023. Material
assumptions are outlined throughout the announcement and include assumptions about the market
price of HPA and funding availability. While Impact considers all the material assumptions to be based
on reasonable grounds, there is no certainty that they will prove correct or that the range of
outcomes indicated by the Scoping Study will be achieved.
Additional funding will be required to achieve the range of outcomes indicated in the Scoping Study.
Investors should note that there is no certainty that Impact can raise financing when needed. It is also
possible that such funding may only be available on terms that dilute or affect the value of Impact’s
existing share capital structure.
Impact has concluded that it has a reasonable basis for providing the forward-looking statements
included in this announcement and believes it has a sound basis to expect it will be able to fund the
development of the project. However, given the uncertainties, investors should not make investment
decisions based solely on the study's results.
Impact Minerals Limited Interactive Investor Hub
ABN 52 119 062 261
61+ 8 6454 6666
Engage with us directly by asking questions, watching video summaries, and
seeing what other shareholders have to say about this and past
announcements at our Investor Hub
https://investors.impactminerals.com.au/welcome
info@impactminerals..com.au
www.impactminerals.com.au
SCOPING STUDY HIGHLIGHTS
The Lake Hope project contains a significant alumina (Al2O3) resource, which could become a
major global supplier of High Purity Alumina (HPA) because of the unique nature of the
deposit that allows very cost-effective mining and processing.
This Scoping Study indicates that, as far as Impact can ascertain from published data, the
Lake Hope project could be one of, if not the lowest-cost producer of HPA globally, possibly
by a significant margin of up to 50%.
Life Of Mine (LOM) Base-Case Financial Metrics
10,000 tpa
4N HPA
initial 25-year
mine life
A$1,334M
A$253M
55%
Post-tax NPV8
Initial Capital
Expenditure
Post-tax IRR
US$3,264/t
A$174M
A$4,877M
Operating cost
(nett of by-product)
Post-tax cash flow per year
Post-tax cashflows
• Potential to become a significant producer of HPA with steady-state production of
10,000 tonnes per annum following a two-year ramp-up.
• Low capital costs compared to peers driven by the unique nature of the clay deposit
at Lake Hope.
• Low operating cost and high margins due to the deposit size, zero strip ratio, highgrade mineralisation at surface, no on-site beneficiation required, advantageous
kinetics of the metallurgical process and by-product credits.
• Natural ESG benefits include probably considerably reduced CO2 emissions compared
to incumbent producers.
• Very favourable market fundamentals with HPA deemed a Critical Mineral in Australia
and many other countries.
ASX:IPT | ABN 52 119 062 261
2
• Forecast compound annual growth rate of about 20% for the HPA and related
products market over the next decade driven by expansion in the battery and LED
sectors.
• The study of HPA is based on a conservative commodity price estimate of US$22,000
per tonne compared to recent forecasts of more than US$25,000 per tonne from
2025 onwards.
Impact Minerals’ Managing Director, Dr Mike Jones, said, “This Scoping Study demonstrates
the world-class potential of the Lake Hope Project and supports what we first thought was
possible when we came across it and the work already done by Roland Gotthard and the Playa
One team”.
“If you are playing in the industrial minerals space, at least one of four things has to be true
about your mine otherwise you will not make it through the market cycle: the deposit has to
be either the biggest, have the highest grade, be the first to market or, preferably, be the
lowest cost producer. The unique characteristics of the Lake Hope deposit, both in terms of
mining and processing, look like they could possibly deliver HPA at the lowest cost globally by
a significant margin”.
“Even though we are only at the Scoping Study stage, with all its inherent uncertainties, the
financial model demonstrates the world-class economics of the project, which has an NPV of
more than A$1 billion, very large operating margins and significant after-tax earnings of
A$174 million per year. The ability to deliver sub-US$4,000 per tonne HPA is an extraordinary
competitive advantage that Impact will continue to leverage in the current Preliminary
Feasibility Study, due for completion in 2024.”
Dr Michael G Jones
Managing Director
ASX:IPT | ABN 52 119 062 261
3
KEY SCOPING STUDY OUTCOMES
Outcome
NPV8 (real post-tax)
Unit
US$
Lake Hope
$934M
Unit Lake Hope
AUD$ $1,334M
NPV10 (real post-tax)
US$
$742M
AUD$ $1,060M
IRR (post-tax)
55%
Capital Costs (10Ktpa)
US$
$177M
AUD$ $252M
Sustaining Capital (25-year
LOM)
Capital Costs (per tonne
capacity)
US$
$142M
AUD$ $1,334M
US$
$17,700
AUD$ $25,285
Operating Costs (AISC)
US$/t HPA
$7,023
AUD$ $10,032
Operating Costs (nett byproduct)
US$/t HPA
$3,264
AUD$ $4,662
Throughput Per Annum
(Clay)
Throughput (Life Of Mine)
Tonnes
46,300
Tonnes
1,157,000
Life Of Mine (Initial)
Years
25
Annual Production (HPA)
Tonnes
10,000
Annual Production (all byproducts)
Tonnes
74,000
Revenue (Life Of Mine)
US$
$6,286M
AUD$ $8,980M
Annual Revenue (Average
LOM)
Annual EBITDA (Average
LOM)
US$
$258M
AUD$ $368M
US$
$175M
AUD$ $250M
Construction period
2 years from FID
Production (Year 1)
Tonnes
5,000
Production (Year 2)
Tonnes
8,000
Production (Steady State)
Tonnes
10,000
Payback period (from FID)
4.5 years
Payback period from first
production
2 years
ASX:IPT | ABN 52 119 062 261
4
SUMMARY OF THE SCOPING STUDY
Impact Minerals Limited (ASX:IPT) is pleased to publish the results of a Scoping Study into a
series of development options for the Lake Hope High Purity Alumina (HPA) Project located
500 km east of Perth in the Tier 1 jurisdiction of Western Australia. The Study comprises the
results of preliminary metallurgical, engineering and logistical studies into the economic
viability of the Lake Hope project.
HPA is now listed as a Critical Mineral in Australia, the US and Europe and is an essential
mineral required for the ongoing decarbonisation of the world’s energy market.
The Scoping Study is reported in accordance with the JORC 2012 Code and ASX Listing Rules
and with a level of accuracy of +/-30% commensurate with this level of study. The Study
justifies the project progressing to a Preliminary Feasibility Study, which is well underway
(ASX Release October 18th 2023).
The Study is based on work completed by Playa One Pty Ltd before Impact’s involvement in
the project and work completed by Impact since acquiring the right to earn an 80% interest
in the project earlier in 2023 (ASX Release March 21st 2023). Impact can earn its 80% interest
by completing the PFS.
The Scoping Study shows that the Lake Hope Alumina Project has the potential to deliver
attractive financial returns due to the unique properties of the Lake Hope Resource, being:
•
•
•
An at-surface sheet of lake clays which will be relatively cheap to mine and with
limited long-term rehabilitation requirements.
There is no requirement for on-site beneficiation because of the very fine-grained
nature of the clay. The mine will be a free digging operation with the transport of
the ore offsite for processing at a permitted industrial site. This contrasts
dramatically with a conventional open pit hard rock mining operation (Figure 1).
No significant infrastructure is required at site, such as power or large quantities
of water.
Figure 1. Comparison of mining techniques between Lake Hope and conventional hard rock mining.
ASX:IPT | ABN 52 119 062 261
5
•
•
•
•
Indicated Resources sufficient to allow a long-life mining operation of more than
25 years.
Mineralisation is amenable to low-temperature acid roasting with low CO2
emissions compared to incumbent producers.
Demonstrated capacity to produce 99.99% HPA from representative material.
Strong ESG Credentials with Heritage Clearance for mining already received.
These advantages could lead to the Lake Hope Alumina Project potentially delivering HPA for
approximately US$3,300 (A$4,714) per tonne nett of by-products, with a post-tax NPV8 of
A$1,334 million (US$933 million) for a capital investment of A$253 million (US$177 million).
This assumes a nominal benchmark production target of 10,000 tonnes per annum of HPA (as
used in feasibility studies by Impact’s peers) with Impact’s metallurgical process models and
using costs similar to current and proposed HPA and similar mining and processing
operations.
This operating cost is significantly lower than costs published by Impact’s peers in several
feasibility studies. For example, Alpha HPA Ltd (US$5,940 and nett of by-products ASX:A4N
Release 17th March 2020), where HPA is produced from a chemical feedstock and FYI
Resources (US$6,217 ASX:FYI Release 8th April 2021) where HPA is produced by hydrochloric
acid leaching of kaolin. These figures are not adjusted for the significant and ongoing inflation
of costs since publication. Impact’s costs are in 2023 dollars.
An in-house cost-curve analysis indicates that at an operating cost of US$3,300 per tonne,
Lake Hope, to the best of Impact’s knowledge, will possibly deliver the lowest-cost HPA
globally (Figure 2).
Figure 2. HPA Industry operating cost curve (costs of new entrants not adjusted for inflation) Existing
OPEX Data sourced from market analyst reports and in-house research.
ASX:IPT | ABN 52 119 062 261
6
The Scoping Study has provided a framework for assessing in more detail the metallurgical,
engineering, logistical, heritage and environmental factors in the work program for the PFS.
Investors should note that the outcomes of the PFS may alter the capital and operational
estimates produced during the Scoping Study, and no investment decision should be based
solely upon the Scoping Study.
PRODUCTION TARGET
The Scoping Study provides a Production Target of 250,000 tonnes of HPA production over
25 years of the project study. The Production Target is based on extraction of an average of
46,300 tonnes of mineralised resources extracted from the Lake Hope deposit. The Lake
Hope Resource comprises 880,000 tonnes of contained alumina at a grade of 25.1% Al2O3,
with 88% of the resource in the higher confidence category of Indicated Resources (Table 1
and ASX Release 19th June 2023). The Production Target is based solely on the extraction of
Indicated Resources only, with no Inferred Mineralisation or Exploration Target material
included in the Production Target.
Impact confirms that there have been no material changes to the Resources Mineralisation
report subsequent to the ASX Release on 19th June 2023.
MATERIAL ASSUMPTIONS and MODIFYING FACTORS
Based on work completed by Playa One Ltd and Impact Minerals, the Scoping Study has made
several material assumptions and used Modifying Factors as defined in the JORC 2012 Code
to assess the project's economic viability. Investors should note that these Material
Assumptions and Modifying Factors are subject to confirmation from ongoing work.
Material Assumptions and Modifying Factors used in this Scoping Study include;
•
The operation's nameplate production is 10,000 tonnes per annum of HPA.
There is no certainty that an operation of this scale will be built. However, based on Impact's
industry analysis, this target has been chosen as a realistic target market share. This is also
the benchmark target used by Impact’s peers (e.g. A4N ASX Release 17th March 2020, and FYI
ASX Release 8th April 2021).
•
That the HPA produced will meet the quality specifications required by customers.
The HPA sighter samples previously produced by Playa One Pty Ltd meet the chemical
specifications required by customers. On-going metallurgical test work as part of the PFS has
so far replicated the Playa One metallurgical process (the patented Sulphate Process), and
therefore, Impact has a reasonable basis to conclude, but cannot guarantee, that it can
reproduce the HPA specification (ASX Release October 18th 2023). In addition, HPA end-user
quality specifications and needs may change, and there is no guarantee that current HPA
product specifications will result in future sales.
ASX:IPT | ABN 52 119 062 261
7
•
The price of 99.99% (4N HPA) realised will be US$22,000 per tonne.
Impact has assumed a discount of about 10% to the commonly perceived basket price of
US$24,000-$25,000 for 4N HPA. Recent independent market analysis indicates prices of
between $US25,000 and upwards of US$30,000 per tonne of milled HPA from 2026 onwards.
However, there is no guarantee that these prices will be achieved.
•
The forecast increase in demand for HPA over the next decade will be realised.
The LED and battery sectors are under constant technological innovation, and there is no
guarantee that HPA demand will rise as forecast should alternatives be found.
•
That by-product and co-product chemicals (agricultural and chemical feedstocks) produced
from the Playa One Sulphate Process will meet customer specifications.
Up to 10% of the project revenue will come from the sale of by-products. Impact needs to
perform marketing and specification research on these by-products and will also require a
greater understanding of the saleability of these chemicals, although they are in high
demand. Variance in revenues from by-products may materially affect future returns.
•
No Native Title impediment exists to the development of the Lake Hope Project mining
operation.
A Heritage Survey has been conducted by the Ngadju Native Title group over the Lake Hope
deposit, with no Aboriginal Cultural Heritage objects or ethnographic sites found. Before the
approval of a mining lease, a mining agreement must be negotiated with all affected Native
Title Parties. Impact has assumed that the terms of this agreement will be agreed upon in the
future.
•
No Environmental impediment exists to the development of the Lake Hope Project mining
operation.
Although a desktop review has indicated no threatened flora or fauna in the area, there is a
risk of finding unrecorded priority ecological communities. Baseline Flora and Fauna Surveys
will start in November 2023. There is no guarantee that environmental factors will not
prevent the development of the mining operation.
•
A suitable site for the HPA facility can be found within the Kalgoorlie region.
Enquiries about the availability of, and conditions surrounding, a processing facility in
Kalgoorlie are at an early stage.
•
The Capital Cost estimate is accurate to within 30%.
The Scoping Study capital costs are an estimate arrived at via analogy with existing operations
and proposed operations of similar scope and scale. Further work is required to finalise the
Lake Hope process flow sheet before undertaking detailed engineering and capital cost
estimation.
•
It takes 30 months to build the Lake Hope processing facility and 18 months to reach
nameplate capacity at 99.99% alumina product quality.
Impact believes these are conservative and achievable time frames.
•
That end-to-end recoveries of alumina are 80%.
Initial work by Playa One indicated end-to-end recoveries of 92% using the patented Playa
One Sulphate Process to produce HPA. Given the unknown performance of the Sulphate
Process at scale, a conservative recovery of 80% alumina has been used.
ASX:IPT | ABN 52 119 062 261
8
•
No debt is assumed. There must be more grounds to believe any debt financing for the
Project because of the early-stage nature of the economic and technical studies. The NPV is
calculated on a 100% equity basis.
•
A discount rate of 8% has been assumed.
•
An exchange rate of US$1 to A$0.70 is assumed.
•
The Scoping Study has been managed by Impact Minerals Limited using several external
consultants for the specialist work. The Study has only been independently reviewed in part.
END OF SUMMARY
The full Scoping Study is attached to this report.
ASX:IPT | ABN 52 119 062 261
9
ASX:IPT | ABN 52 119 062 261
10
1.
PROJECT OVERVIEW
The Lake Hope High Purity Alumina (HPA) Project is an integrated mine and metallurgical
processing operation proposed to be developed over the next few years in the Tier 1
jurisdiction of Western Australia.
The mine will be located on E63/2086, about 500 km east of Perth. It will supply an aluminamineralised clay to a processing plant, most likely in Kalgoorlie, that will convert the clay into
High Purity Alumina with a purity of 99.99% Al2O3 (so-called 4N, short for four nines) or
better. Alumina is the name given to aluminium oxide with the formula Al2O3.
2.
PROJECT OWNERSHIP
The Lake Hope Project covers numerous prospective salt lakes between Hyden and
Norseman in southern Western Australia and comprises eight granted exploration licences
that are poorly explored (E63/2086, EL63/2317-19, EL63/2730, EL74/673 EL74/764 and
EL74/779). The tenements cover about 238 km2 and are all 100% owned by Playa One Pty
Limited.
Impact has the right to earn an interest in the company Playa One Pty Limited as follows (ASX
Releases 1st and 4th May 2023):
1. Upon completion of a Preliminary Feasibility Study (PFS), Impact can elect to enter an
incorporated joint venture with the Playa One shareholders (through an entity
representing them, Playa Two Pty Ltd). If so, it will acquire an immediate 80% interest
in Playa One by issuing up to 120 million fully paid ordinary shares capped at a
maximum value of $8 million (based on the 5-day VWAP before the election) to Playa
One Shareholders.
2. Upon completion of a Definitive Feasibility Study to be sole-funded by Impact, Impact
will issue up to 100 million fully paid ordinary shares capped at a maximum value of
$10 million (based on the 5-day VWAP before the ASX announcement of the
completion of the DFS) to the Playa One Shareholders.
3. Playa One shareholders will be free-carried to a Decision to Mine. Impact will
maintain all Playa One tenements in good standing during this time.
4. If a Decision to Mine is made, the Playa One Shareholders may contribute to mine
development costs or be diluted. If their interest falls below 7.5%, it will convert to a
2% net smelter royalty.
ASX:IPT | ABN 52 119 062 261
11
3.
MANAGEMENT OF THE SCOPING STUDY
The Scoping Study and the complimentary and ongoing PFS are managed by Roland
Gotthard, who discovered the Lake Hope Project and joined Impact as Project Manager.
The Company has appointed independent consultants and experienced contractors to
provide advice and costs for the various parts of the studies and contribute to the current
state of knowledge for the project outlined in this report.
The following consultants are providing advice:
Mineral Resource Estimation: H and S Consultants, Brisbane. H and S are well-known
resource estimation specialists with specific experience in resource estimation for deposits in
Western Australian Playa lakes.
Environment: Biota, a respected environmental consultancy with Biota Environmental
Sciences, a consultancy specialising in flora, fauna and ecological studies for environmental
impact assessment. Biota is also providing advice about the approvals process for the grant
of a Mining Lease.
Mining: The Mining Engineer (TME) Mining Consulting, an independent mining engineering
consultant with experience in mine design, scheduling, and work within near-surface mineral
deposits.
Metallurgy: ALS Metallurgy Pty Ltd manages and conducts the metallurgical test work and
laboratory services for the ongoing PFS work stream. Strategic Metallurgy, a specialised
consultant, has been engaged for process design and modelling.
Logistics: Qube Logistics Pty Ltd has provided scoping-level advice on the logistical aspects of
the project, such as haulage costs for ore and reagents.
Financial Modelling: Platek Analytics has reviewed and built upon Impact’s internal economic
model for the Scoping Study and will continue to do so for the PFS.
Marketing: Impact has advanced discussions with various marketing and trading houses to
build a network of contacts for marketing the Lake Hope alumina products.
ASX:IPT | ABN 52 119 062 261
12
4.
PROJECT LOCATION
The Lake Hope project is about 135 km east of Hyden and about 500 km east of Perth in
Western Australia and is centred on two small salt lakes about 25 km south of the
Norseman-Hyden road (Figure 1). A track goes from the road directly to the lakes (Figure 2).
High-grade alumina-bearing clay mineralisation occurs in the top two metres of the lake
beds, and the project aims to produce HPA by shallow open pit mining of that clay and
transport it via the Norseman-Hyden Road to Kalgoorlie for processing.
Figure 1. Location of the Lake Hope HPA Project.
5.
GEOLOGY
The salt lakes of Western Australia are well known for their unique and complex
hydrogeochemistry, which has led to the formation of a wide variety of economic minerals
and brines within the playa systems. These include the world-class Yeelirrie uranium deposit
(>100 Mlb U3O8), significant resources of potash brines, gypsum and lime-sand.
Playa One identified the Lake Hope area as having unique climatic and geological
characteristics that have led to the formation of what may be a globally unique deposit of
alumina-rich material within the surficial clay of two small salt lakes, or “pans”, in the larger
Lake Hope playa system. These pans are called West Lake and East Lake and are surrounded
by various sand dunes and weathered granite outcrops (Figures 2 and 3).
The lake clays, which are only up to a few metres thick, have unique chemical and physical
properties and consist almost entirely of alumina-bearing minerals that are plasticine-like in
consistency and can be sampled with hand-held augers and push tubes (Figures 4 and 5).
ASX:IPT | ABN 52 119 062 261
13
Track
Figure 2. West Lake and East Lake within E63/2086 (blue rectangle). Note the track, which extends
from the Norseman-Hyden Road, thus eliminating significant clearing for access.
Figure 3. Geology of the Lake Hope HPA Project.
ASX:IPT | ABN 52 119 062 261
14
Figure 4. Lake Hope showing the push tube sampling method (!) and an example of the
lake clay from the push tube.
Particle size distribution analysis demonstrates that virtually all the minerals within the lake
clay are less than a few microns in size and that between 80% and 90% of them are less than
300 nanometres in size (Figure 5).
These unique characteristics have produced a near-perfect mineral deposit for mining - a
very high-value end-product whose parent material is:
•
very soft and shallow, allowing for extremely cheap quarrying with limited
infrastructure requirements, no pre-stripping, no selective mining, a tiny
environmental footprint, and limited rehabilitation requirements.
•
naturally fine-grained with no need for crushing and grinding, allowing for
transport to an off-site processing facility that can be built at an existing industrial
site. In essence, this is equivalent to Direct Shipping Ore (DSO) and
•
comprises a few minerals that require only simple washing before acid leaching,
thus allowing for low-cost, straightforward metallurgical processing.
ASX:IPT | ABN 52 119 062 261
15
Figure 5. Scanning Electron Microscope imagery of <300nm clay particles.
6.
MINERAL RESOURCES
The Lake Hope deposit has a mineral resource that comprises 880,000 tonnes of contained
alumina at a grade of 25.1% Al2O3, with 88% of the resource in the higher confidence
category of Indicated Resources (Table 1 and ASX Release 19th June 2023). A block model
plan view of the resource is shown in Figure 6. Only Indicated Resources have been included
in this study.
Category
Indicated
Inferred
Total
Indicated
Million tonnes
West Lake
2.09
0.23
2.32
East Lake
1.10
Inferred
0.08
Total
1.18
Alumina %
Al2O3 Tonnes
25.5%
23.2%
25.3%
534,600
52,300
586,900
24.8%
273,400
24.1%
19,400
24.8%
292,800
25.3%
23.4%
25.1%
808,000
71,700
879,700
Combined
Indicated
Inferred
Total
3.19
0.31
3.50
Table 1. Lake Hope Alumina Mineral Resources.
ASX:IPT | ABN 52 119 062 261
16
The Mineral Resource Estimate was prepared by resource consultants H and S Consultants
(H&SC) of Brisbane, Queensland. It has been reported in accordance with the Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, the JORC
Code (2012). Impact confirms that no new information exists, and all modifying factors
remain the same as at the time of the first publication of the resource (ASX Release June 19th
2023).
The Mining Studies for this Scoping Study have focused on the highest-grade parts of the
Lake Hope alumina deposit. Mining will initially excavate the parts of the deposit with greater
than 27% Al2O3 (about 360,000 tonnes or 97,000 tonnes of contained alumina). After that,
the greater than 25% Al2O3portion would be extracted (Figure 6).
This is sufficient to supply material to the processing plant for the first ten years of
production at the benchmark production rate of 10,000 tonnes per year of HPA.
West Lake
East Lake
Figure 6. Alumina Block Grade Distribution for the Lake Hope Mineral Resources.
ASX:IPT | ABN 52 119 062 261
17
7.
DEVELOPMENT SCENARIO and MODIFYING FACTORS
Investors should note that the development of the Lake Hope HPA Project proposed here is
preliminary, and further significant work is required to confirm its economic viability.
The project aims to extract alumina from the lake clays at Lake Hope and transport them to
Kalgoorlie to be processed in a purpose-built facility via the patented and proprietary socalled Playa One Sulphate Process. This hydrometallurgical process has been shown to have
the technical capacity to produce 4N HPA (ASX Release March 21st 2023).
This Scoping Study is aimed at demonstrating the economic viability of the project under a
base case scenario with the following material assumptions and modifying factors, which are
described in more detail at the front and end of this report:
•
The nameplate production capacity of the operation is 10,000 tonnes per annum of
HPA production with a minimum purity of 99.99% Al2O3. This would account for
between 10-15% of global production as forecast in 2027, the forecast year of
nameplate production.
•
The HPA produced will meet the quality specifications required by customers.
•
The price of 99.99% (4N HPA) realised will be US$22,000 per tonne.
•
The Mineral Resources justify an operation with a minimum mine life of 25 years.
•
By-product chemicals (agricultural and chemical feedstocks) produced from the Playa
One Sulphate Process will meet customer specifications.
•
No Native Title impediment exists to the development of the Lake Hope Project
mining operation.
•
No Environmental impediment exists to the development of the Lake Hope Project
mining operation.
•
The Capital Cost estimate is accurate to within 30%.
•
A suitable site for the HPA facility can be found within the Kalgoorlie region.
•
It takes 30 months to build the Lake Hope processing facility and 18 months to reach
nameplate capacity.
•
Hydrometallurgical treatment of mineralisation via the Playa One Sulphate Process is
successful, with 80% end-to-end recovery of alumina.
•
A discount rate of 8% is assumed.
•
No debt is assumed.
•
The Scoping Study has been managed by Impact Minerals Limited using several
external consultants for the specialist work. The Study has yet to be independently
reviewed in whole.
ASX:IPT | ABN 52 119 062 261
18
8.
MINING
The mine plan, prepared by TME Mine Consulting, envisages campaign mining with the
excavation of 140,000 tonnes of lake clay grading 27% Al2O3 from the top one to two metres
of the lake ore every three years and an annual drawdown of about 46,300 tonnes per year.
This is needed to reach the yearly benchmark production rate of 10,000 tonnes of HPA. The
mining would comprise a 94-day digging cycle every three years in the dry months between
November and March.
TME have provided mine schedules, plant and equipment schedules, and a cost base for a
preferred mining fleet comprising an excavator (20-tonne capacity) and seven to eight
10-tonne capacity tracked dump