Breakthrough alternative HPA metallurgy route at Lake Hope
Released
Released
Announcement PDF
ASX Code: IPT
FEBRUARY 27, 2024
CORPORATE RELEASE
Breakthrough alternative High Purity Alumina (HPA) metallurgy route
revealed at the Lake Hope Project, WA
•
•
•
•
•
99.99% (4N) Al2O3 produced from a new low-temperature leach (LTL) and acid digestion process
called the “LTL Process”:
The LTL Process is a simpler process that may lower the Capital and Operating Costs to produce HPA
compared to the Sulphate Process, which has been the focus of test work to date.
The Sulphate Process underpinned the recent Scoping Study, which indicated an operating cost of
<US$4,000 per tonne of HPA, up to 50% lower than Impact’s peers and an NPV8 of A$1.3 billion.
The LTL Process will now be included in the ongoing Pre-Feasibility Study in parallel with the
Sulphate Process at marginal extra cost to determine the best processing route to HPA.
The PFS is due to be completed on schedule in late 2024.
Impact Minerals’ Managing Director, Dr Mike Jones, said, “Today we reveal a further exciting breakthrough
for producing HPA from the unique mix of minerals that are present at Lake Hope, minerals which have
allowed our new LTL Process to produce the benchmark 99.99% pure HPA very quickly after starting the test
work.
The LTL Process is simpler than the Sulphate Process that underpinned our recent Scoping Study and showed
that at less than US$4,000 per tonne, Lake Hope may produce HPA at up to 50% cheaper than our peers.
We think that further work on the LTL Process could result in even lower operating and capital costs, and
this would only further enhance the already impressive economics of the project, which has an NPV 8 of well
over A$1 billion.
We have now started further optimization studies for the LTL Process and will push forward with our PreFeasibility Study using both process routes for the time being to determine the best strategic choice for
processing at the project. Given we can run all these tests in parallel for little extra cost, we are still on
course to finish the PFS later this year and continue to look forward towards producing HPA from Lake
Hope”.
Figure 1. Location of the Lake Hope Project.
A new proprietary metallurgical process has been identified for producing high-value High Purity Alumina
(HPA) from the lake clays at Impact Minerals Limited’s (ASX:IPT) Lake Hope project, located 500 km east of
Perth in Western Australia (Figure 1). Impact can earn an 80% interest in Playa One Pty Limited, which owns
the Lake Hope project, by completing a Pre-Feasibility Study (PFS) on the project which is in progress (ASX
Release March 21st 2023 and November 9th 2023).
The new process, called the LTL Process, has produced High Purity Alumina (HPA) at 99.99% purity from the
raw lake clay in only a few months of laboratory test work (with its attendant delays for holidays and other
customer work) (Table 1). This is one of the fastest times to produce HPA from raw materials reported by
ASX-listed companies and attests to the relatively straightforward nature of the process. It involves different
reagents to those used in the Playa One Sulphate Process, which has also recently successfully produced 4N
HPA (ASX Release 19th February 2024).
Sample
ID
Total 66
elements ppm
%HPA
Elemental
As
ppm
B
ppm
Ca
ppm
Cr
ppm
Cu
ppm
Fe
ppm
K
ppm
Mg
ppm
Na
ppm
Ni
ppm
P
ppm
S
ppm
Si
ppm
HY17154
104.82
99.990
0.005
1.408
10.83
1.176
1.103
17.58
1.254
20.38
1.999
1.323
2.899
7.157
30.620
HY17154
105.98
99.989
0.005
1.017
11.67
1.128
1.159
20.80
1.483
19.94
1.888
1.470
3.370
8.554
27.290
Table 1. Assays results for Lake Hope HPA via the LTL Process. Repeat samples derived from sample LHMET001 (see
Table below for sample location). Assays units are parts per million (ppm).
Note that the LTL Process has not been optimized and further reductions in contaminants are anticipated.
The LTL Process is a direct low-temperature leach (<90o C) that removes the requirement for sulphuric acid
roasting, which was a key part of the Sulphate Process and reduces the number of steps to produce HPA
from five stages to four (Figure 2). Accordingly, the new process could offer further reductions in operating
costs and capital costs to produce HPA compared to the Playa One Sulphate Process.
The recently released Scoping Study on Lake Hope, which was based on the Sulphate Process, showed that
at an operating cost of less than US$4,000 per tonne, Lake Hope could be the lowest-cost producer of HPA
globally by a significant margin of up to 50% over Impact’s peers (ASX Release November 9 th 2023).
Therefore, this margin could be increased should test work on the new process support these initial results
and further demonstrate the potential world-class economics of the Lake Hope project.
ASX:IPT | ABN 52 119 062 261
In addition, the LTL Process is not yet fully optimized, and improved recoveries (currently 84.7% of the raw
alumina) and further reductions in contaminants are expected as test work progresses.
Like the Sulphate Process, the LTL Process also produces a fertilizer by-product, which is likely to be a key
factor in offsetting the operating cost to produce 4N HPA.
LTL Process
Sulphate Process
Figure 2. A comparison of the LTL Process and the Sulphate Process.
Background
The Lake Hope Project contains a unique deposit of clay, which contains about 880,000 tonnes of alumina
(Al2O3) in the top two metres of two small salt lakes on E63/2086. The deposit comprises Indicated (88%)
and Inferred (12%) Resources of 3.5 million tonnes at an average grade of 25.1% alumina (see Table at the
back of this report and ASX Release 19th June 2023 for details). Impact can earn an 80% interest in Lake
Hope from Playa One Pty Limited by completing a Pre-Feasibility Study, which is in progress (PFS).
The alumina in the lake clay can be converted into HPA via Playa One’s proprietary and patented ‘Sulphate
Process”, and this has been the focus of metallurgical test work to date and was used as the basis for the
Scoping Study (ASX Releases March 21st 2023, October 18th 2023 and November 9th 2023).
As part of ongoing metallurgical research, Playa One has identified two other potential pathways to HPA and
associated valuable by-products, including the new LTL Process. Results from the third process are due early
in the next Quarter.
Next Steps
The PFS at Lake Hope is progressing on schedule and is due for completion in late 2024. Metallurgical test
work is the critical component of the work to be completed for the PFS and is the focus of the forward work
programme, which will now include batch production from both the Sulphate Process and LTL Process (ASX
Release February 19th 2024). The test work will be completed on both processes in parallel at marginal extra
cost and time. Final optimization of the LTL Process and preliminary economic studies will be completed as
part of this work.
All of these results, and results from the third possible process route, are due in the next Quarter. This will
allow a final choice to be made of the process route required for commercial production of HPA.
Given the potential for chemical and fertilizer products as a valuable by-product from both the Sulphate
Process and the LTL Process, an assessment of the mineral potential of the wider Lake Hope playa system is
in progress. This has involved some preliminary shallow auger and push tube drilling, and a detailed review
and interpretation of the results is in progress.
ASX:IPT | ABN 52 119 062 261
Dr Michael G Jones
Managing Director
Sample Information
Sample
MGA E
MGA N
Source
Al2O3%
K2O%
Fe2O3%
CaO%
Na2O%
SiO2%
MgO%
MnO%
P2O5%
LHMET001
243,880
6,409,250
East Lake
28.77
7.25
3.03
0.05
3.29
15.8
0.79
x
0.082
Assay and Metallurgical Information
All testing was undertaken at ALS Metallurgy Pty Ltd, Balcatta, Western Australia, under the supervision of a
qualified metallurgist. All data is presented as received. Assays were undertaken at ALS Geochemistry using 4Acid digestion with ICP-OES multi-element quantification or lithium borate fusion with XRF finish, where
appropriate. The metallurgical testing is incomplete, and results are preliminary in nature.
Resource Statement
The Mineral Resource Estimate for Lake Hope is:
Category
Million tonnes
Alumina %
Al2O3 Tonnes
West Lake
Indicated
2.09
25.5%
534,600
Inferred
0.23
23.2%
52,300
Total
2.32
25.3%
586,900
East Lake
Indicated
1.10
24.8%
273,400
Inferred
0.08
24.1%
19,400
Total
1.18
24.8%
292,800
Combined
Indicated
3.19
25.3%
808,000
Inferred
Total
0.31
3.50
23.4%
25.1%
71,700
879,700
The resource statement was first made to the ASX on June 19th 2023. There are no factors that Impact is
aware of that have changed the material assumptions made at that time.
Competent Persons Statement
The review of metallurgical results contained in this report is based on information compiled by Mr Roland Gotthard, a
Member of the Australasian Institute of Mining and Metallurgy and a consultant to Impact Minerals Limited. He has
sufficient experience which is relevant to the style of mineralisation and types of deposits under consideration and to the
activity that he is undertaking to qualify as a Competent Person as defined in the 2012 edition of the Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code). Mr Gotthard has consented to the
inclusion in the report of the matters based on his information in the form and context in which it appears.
ASX:IPT | ABN 52 119 062 261
JORC Code, 2012 Edition – Table 1
Section 1 Sampling Techniques and Data
Criteria
JORC Code explanation
Commentary
Sampling techniques
•
Nature and quality of sampling (e.g. cut channels,
random chips, or specific specialised industry standard
measurement tools appropriate to the minerals under
investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
•
Sampling comprised a representative 10kg sample dug from a pit.
•
Samples were obtained from 0.5 to 1m depth with a weight of ~10kg, with the whole
sample bagged in plastic buckets.
•
Sample preparation and analysis was completed at a commercial laboratory (Intertek
WA) using industry standard practices.
•
Include reference to measures taken to ensure sample
representivity and the appropriate calibration of any
measurement tools or systems used.
•
Metallurgical samples are representative powders produced in the laboratory using
normal metallurgical processes.
•
Aspects of the determination of mineralisation that are
Material to the Public Report.
•
Description of ‘industry standard’ work
Drilling techniques
•
Drill type (e.g. core, reverse circulation, open-hole
hammer, rotary air blast, auger, Bangka, sonic, etc) and
details (e.g. core diameter, triple or standard tube,
depth of diamond tails, face-sampling bit or other type,
whether core is oriented and if so, by what method, etc).
•
Not applicable to metallurgical sample.
Drill sample recovery
•
Method of recording and assessing core and chip sample
recoveries and results assessed.
•
Not applicable to metallurgical sample.
•
Measures taken to maximise sample recovery and
ensure representative nature of the samples.
•
Whether a relationship exists between sample recovery
and grade and whether sample bias may have occurred
due to preferential loss/gain of fine/coarse material.
•
Whether core and chip samples have been geologically
and geotechnically logged to a level of detail to support
appropriate Mineral Resource estimation, mining studies
and metallurgical studies.
•
Mineralisation collected in LHMET001 is visually and chemically identical to material
throughout the East Lake.
•
Mineralogy is impossible to determine visually.
•
Logging is qualitative in nature as the grain size is too fine to allow visual
identification of mineralogy even under hand lens or electron microscope.
•
Metallurgical samples were collected by Impact Minerals staff.
•
Metallurgical samples were prepared, treated, and prepared for assay by ALS
Metallurgy using industry standard techniques.
Logging
Sub-sampling techniques and
sample preparation
•
Whether logging is qualitative or quantitative in nature.
Core (or costean, channel, etc) photography.
•
The total length and percentage of the relevant
intersections logged.
•
If core, whether cut or sawn and whether quarter, half
or all core taken.
•
If non-core, whether riffled, tube sampled, rotary split,
etc and whether sampled wet or dry.
•
•
Quality control measures are observed by the metallurgical laboratory.
For all sample types, the nature, quality and
appropriateness of the sample preparation technique.
•
•
The metallurgical results are consistent with initial test work stages and are not the
final embodiment of the process.
Quality control procedures adopted for all sub-sampling
stages to maximise representivity of samples.
•
The grain size of the mud sample is nanometre size and sample size is appropriate.
•
Sub-sample sizes presented for metallurgy are considered appropriate and
representative.
•
LHMET001 is considered representative of higher grade material from the Lake Hope
mineral resource.
•
Quality of assay data and
laboratory tests
•
Whether sample sizes are appropriate to the grain size
of the material being sampled.
•
The nature, quality and appropriateness of the assaying
and laboratory procedures used and whether the
technique is considered partial or total.
•
LHMET samples were assayed via lithium borate fusion and XRF quantification via
FB1/XRF10 or FB1/XRF30. The technique is considered a total digest technique.
•
•
The assay method is considered appropriate for the material and elements reported.
For geophysical tools, spectrometers, handheld XRF
instruments, etc, the parameters used in determining
the analysis including instrument make and model,
reading times, calibrations factors applied and their
derivation, etc.
•
Sampling methodology at ALS is considered industry standard for metallurgical
processing test work.
•
Metallurgical solids are assayed by ALS Geochemistry using 4-acid or fusion digests
and ICP-MS or XRF quantification, respectively. These are considered total digestions.
Nature of quality control procedures adopted (e.g.
standards, blanks, duplicates, external laboratory
checks) and whether acceptable levels of accuracy (i.e.
lack of bias) and precision have been established.
•
Metallurgical liquors are assayed via solution ICP-MS and halides by ISE.
•
Percent extractions are calculated by ALS Metallurgy based on solid and liquid assays
and sample masses.
•
High Purity Alumina is defined by summing the known elemental concentrations of all
elements besides aluminium, oxygen, nitrogen and hydrogen, where known, and
subtracting from 100%.
•
The detection limits for most elements assayed here are too high to define alumina as
HPA.
The verification of significant intersections by either
independent or alternative company personnel.
•
LHMET001 has been assayed at Intertek and at ALS Laboratories.
•
•
Metallurgical samples have not been independently verified.
The use of twinned holes.
•
•
Documentation of primary data, data entry procedures,
data verification, data storage (physical and electronic)
protocols.
Data is stored on a professional relational database maintained by Impact Minerals
Limited.
•
Assays below detection limit of the respective methodology are highlighted.
•
Verification of sampling and
assaying
Location of data points
Measures taken to ensure that the sampling is
representative of the in-situ material collected, including
for instance results for field duplicate/second-half
sampling.
•
•
Discuss any adjustment to assay data.
•
Accuracy and quality of surveys used to locate drill holes
(collar and down-hole surveys), trenches, mine workings
and other locations used in Mineral Resource
estimation.
•
A table of sample locations is provided in the report.
•
Sample locations recorded with handheld GPS accurate to within 1m.
•
MGA Zone 50 South.
•
Specification of the grid system used.
•
Topographic control is provided by DGPS and drone topographic control.
•
Quality and adequacy of topographic control.
ASX:IPT | ABN 52 119 062 261
Criteria
JORC Code explanation
Commentary
Data spacing and distribution
•
Data spacing for reporting of Exploration Results.
•
No new exploration results are reported here.
•
Whether the data spacing and distribution is sufficient to
establish the degree of geological and grade continuity
appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.
•
Not applicable as there was no drilling.
•
Whether sample compositing has been applied.
•
Whether the orientation of sampling achieves unbiased
sampling of possible structures and the extent to which
this is known, considering the deposit type.
•
The mineralization is considered representative of the mineral deposit from which is
sourced.
•
If the relationship between the drilling orientation and
the orientation of key mineralised structures is
considered to have introduced a sampling bias, this
should be assessed and reported if material.
•
The measures taken to ensure sample security.
•
Samples were sealed in individually numbered plastic buckets and bags with zip ties.
•
Samples were delivered to the laboratory directly by company personnel to ensure
complete chain of custody.
•
No audits or reviews of sampling techniques and data have been completed.
Orientation of data in relation
to geological structure
Sample security
Audits or reviews
•
The results of any audits or reviews of sampling
techniques and data.
Section 2 Reporting of Exploration Results
Criteria listed in the preceding section also apply to this section
Criteria
JORC Code explanation
Commentary
Mineral tenement and land
tenure status
•
Type, reference name/number, location and ownership
including agreements or material issues with third
parties such as joint ventures, partnerships, overriding
royalties, native title interests, historical sites,
wilderness or national park and environmental settings.
•
E63/2086 Lake Hope
•
E63/2317
•
E63/2318
•
E63/2319
The security of the tenure held at the time of reporting
along with any known impediments to obtaining a
licence to operate in the area.
•
E64/673
•
E64/674
•
100% Playa One Pty Ltd
•
Native Title Agreements are in place with Native Title parties.
•
Heritage Surveys have been conducted and no Aboriginal Cultural Heritage exists over
the mineralization or Mineral Resource.
•
No national parks, nature reserves or other licences interact with E63/2086.
•
Exploration done by other
parties
•
Acknowledgment and appraisal of exploration by other
parties.
•
Nil.
Geology
•
Deposit type, geological setting and style of
mineralisation.
•
Mineralisation comprises a flat-lying evaporitic lake sequence and is bound by the
margins of the lake by sand dunes.
•
Mineralisation comprises light brown to light grey, dense, plasticine consistency salt.
•
The salt is a nanometre sized colloidal precipitate of aluminium minerals and silica.
•
Salt lakes within evaporitic basins within the granite terrane of the Yilgarn Craton,
Western Australia.
•
Lacustrine evaporite sulphate salts hosted within flat-lying sheet deposits.
•
All drill hole information has previously been reported.
•
No exploration results are reported in this disclosure.
Drill hole Information
Data aggregation methods
•
A summary of all information material to the
understanding of the exploration results including a
tabulation of the following information for all Material
drill holes:
•
easting and northing of the drill hole collar
•
elevation or RL (Reduced Level – elevation above sea
level in metres) of the drill hole collar
•
dip and azimuth of the hole
•
down hole length and interception depth
•
hole length.
•
If the exclusion of this information is justified on the
basis that the information is not Material and this
exclusion does not detract from the understanding of the
report, the Competent Person should clearly explain why
this is the case.
•
In reporting Exploration Results, weighting averaging
techniques, maximum and/or minimum grade
truncations (e.g. cutting of high grades) and cut-off
grades are usually Material and should be stated.
•
Where aggregate intercepts incorporate short lengths of
high-grade results and longer lengths of low grade
results, the procedure used for such aggregation should
be stated and some typical examples of such
aggregations should be shown in detail.
•
The assumptions used for any reporting of metal
equivalent values should be clearly stated.
ASX:IPT | ABN 52 119 062 261
Share your feedback
Discover