Quarterly Activities Report
Released
Released
Announcement PDF
30th OCTOBER 2024
CORPORATE ANNOUNCEMENT
SEPTEMBER 2024 QUARTERLY REPORT
HIGHLIGHTS
1. Lake Hope High Purity Alumina (HPA) Project, WA (IPT earning 80%)
•
The Mine at Lake Hope:
o A negotiation protocol for Land Access and Cultural Heritage
agreements with the Ngadju peoples reviewed and signed.
o Applications for a Mining Lease and associated Miscellaneous licence
lodged.
o Infill drilling to define a maiden Measured Resource and Proven
Reserve completed with resource calculations and economic studies
in progress.
o Mining studies underway to provide mining schedules, proposed
equipment, site logistics and costs of mining and transport of ore
to Kwinana.
o
•
•
Further flora fauna and heritage surveys are being planned for the
mine haul road.
The Process Plant:
o Kwinana selected as the location for process plant to produce a
benchmark 10,000 tonnes per annum of HPA due to access to
providers of the required input chemical reagents, buyers of the
fertiliser and acid by-products and access to suitable land. Combined,
these provide substantial strategic advantages for the project with
savings on capex and opex.
o The Low-Temperature Leach process selected as the most
straightforward processing method to produce HPA at scale.
o CPC Engineering selected to provide a design and engineering study
for the full-scale plant that is underway.
Product development, offtake and marketing
o Further test work on HPA and fertiliser by-products continues.
o Experimental work has produced a hydrated alumina product that
may have major applications in the catalyst and flame retardant
industries.
o Early-stage discussions are underway for potential synergies with
existing alumina businesses in Europe and the USA.
o A marketing and product development team is being assembled.
COMPANY DETAILS
Market Cap: A$39.8m (0.013 p/s)
Issued Capital: 3,059,433,718
ABN 52 119 062 261
9 Richardson Street
West Perth
Western Australia 6005
Phone: +61 (8) 6454 6666
Email:
info@impactminerals.com.au
Website: impactminerals.com.au
DIRECTORS
Mr Peter Unsworth
Chairman
Dr Michael Jones
Managing Director
Mr Paul Ingram
Non-Executive Director
Dr Frank Bierlein
Non-Executive Director
Mr Arron Canicais
Company Secretary
2. Arkun-Beau, WA (IPT 100%)
•
•
•
•
No major no activity occurred this quarter, though efforts remain on track to resume exploration
after the cropping season ends in the wheatbelt in December.
413 soil samples were re-assayed to refine drill targets at Beau and Caligula prospects
Land access agreements and statutory approvals are being finalised ahead of planned drill
programme in Q1 2025
Previous geochemical and MME survey data at Caligula support the project potential, with $180,000
co funding awarded under the WA Government’ EIS scheme for drilling.
3. Corporate/Finance
• A FY23 Research and Development Rebate of $395,000 was received during the Quarter.
2|Page
ASX ANNOUNCEMENT
PROJECT REPORTS
1. LAKE HOPE HIGH PURITY ALUMINA PROJECT, WA (IPT earning 80%)
Figure 1. Location of the Lake Hope Project and proposed haul route to Kwinana.
During the Quarter Impact Minerals announced that it had lodged a Mining Lease Application (MLA63/684)
and associated Miscellaneous Licence (L63/99) for the Lake Hope High Purity Alumina (HPA) Project located
500 km east of Perth in Western Australia, (Figures 1 and 2). This is a crucial step in advancing the project
towards production as it defines the work required to obtain the statutory approvals needed for the grant of
the Mining Lease.
The approvals process, together with the logistics and estimated costs of mining and transporting the Lake
Hope mud to the process plant, form one of the four key parts of a Pre-Feasibility Study (PFS) on Lake Hope,
which is in progress (Figure 3 and ASX Release July 10th, 2024). Impact can take an 80% interest in Playa One
Pty Limited, which owns the Lake Hope Project and associated intellectual property, by completing the PFS
(ASX Releases March 21st 2023 and July 10th 2024).
The PFS followed on from a positive Scoping Study, which showed that for a benchmark production of 10,000
tonnes per annum of HPA, the Project has an estimated post-tax Net Present Value (NPV8) of about A$1.3
billion and would potentially be one of the lowest-cost producers of HPA globally (ASX Release November 9th
2023).
3|Page
ASX ANNOUNCEMENT
All material assumptions underpinning the production target and the forecast financial information derived
from it in the Scoping Study continue to apply and have not materially changed within the +/-30% parameters
(ASX November 9th, 2023).
Figure 2. Location of the Mining Lease and Miscellaneous Licence Applications at Lake Hope.
Exploration licences under Impact’s control are shown in blue. An access agreement will be required with Kingsland
Minerals Limited who the green tenements. Initial discussions for this have been very positive.
The Mine
As part of the Pre-Feasibility Study the following work has been completed or is in progress.
1. Discussions were held with the Prescribed Body Corporate (PBC) for the Ngadju Aboriginal people to
inform them of Impact’s intention to develop the Project and to lodge a Mining Lease Application. A
Negotiation Protocol was received from the PBC for Impact’s review, which set’s the framework for
negotiations to achieve a Land Access Agreement and a Cultural Heritage Management Plan for the
mine and the potential benefits to the Ngadju community from the development of the Lake Hope
mine.
2. A mineralisation report, a Mining Lease layout, and a Miscellaneous Licence for haul road access and
site logistics were finalised for the Mining Lease application (Figure 2). Areas of gravel and construction
materials for the haul road have been identified and mapped as part of this work. The haul road
location offers considerable savings in the capital expenditure required for road construction
compared to upgrading existing tracks.
4|Page
ASX ANNOUNCEMENT
3. Infill drilling on the West Lake was completed to convert a significant portion of the previously defined
Indicated Resource to a Measured Resource and sufficient to provide a minimum 15-year mine life.
This will allow a maiden Proven Reserve to be declared with further mining and economic studies. H
and S Resource Consultants are preparing the resource upgrade.
4. Quotes are being sought for follow-up seasonal flora and fauna surveys that will be required along the
haul road and proposed gravel pits. In addition, further Heritage Surveys will be needed along the
same infrastructure and will likely occur next year as discussions with the Ngadju peoples and the
statutory approvals process progress.
The Process Plant
1. Kwinana has been selected as the best location for the processing plant following a rigorous study of
the available options. This is a key outcome of the PFS, and the decision was driven by the ready
availability of the various chemical reagents needed for the process plant compared to the transport
cost to get reagents to Kalgoorlie, which was the basis of the Scoping Study (ASX Release November 9th
2023). The savings in operating costs far outweigh the marginal extra cost of transporting ore to
Kwinana rather than Kalgoorlie.
2. Another key outcome of the PFS is selecting the Low-Temperature Leach (LTL) process as the most
effective process for producing HPA at scale (ASX Release February 27 th 2024). This follows ongoing
test work and financial modelling for the LTL and Sulphate Processes.
3. Discussions are underway with potential suppliers of the input reagents required for the LTL process
and potential buyers of the associated fertiliser and acid by-products. Indications are that both the
required inputs and by-product outputs can be provided “at the gate” in Kwinana. This is a significant
strategic advantage for the project, minimises the requirement for many minor capital items, and leads
to savings in operating costs.
4. A block of land has been identified as suitable for the plant, and discussions are underway to secure it
when appropriate.
5. CPC Engineering was commissioned to undertake design engineering studies and provide estimates of
the capital and operating costs for a process plant to produce 10,000 tonnes per annum of HPA. These
costs will be used in the PFS. CPC’s work will build on extensive Process Flow Design and Mass Flow
Balance calculations recently completed by Strategic Metallurgy.
Test Work
1. Metallurgical test work is progressing well, and production of HPA samples is underway. Work is
progressing on both the sulphate process and low temperature leach process (LTL) and now includes
further mass flow balance and process flow design work with a particular focus on acid usage and
regeneration at the back end of the processes (ASX Releases 19th February 2024 and 27th February
2024). In addition, further test work is underway on the fertiliser by-product to help determine likely
demand and pricing.
5|Page
ASX ANNOUNCEMENT
1. Detailed discussions are in progress regarding the design and construction of a pilot plant that will
produce HPA of consistent quality for potential offtake partners. On October 22nd 2024, Impact
announced that it had been awarded a grant of $2.87 million grant in collaboration with CPC
Engineering and the Mineral Recovery Research Centre (MRRC) at Edith Cowan University, towards the
commercialisation of the company’s innovative process to produce High Purity Alumina (HPA) from the
Lake Hope deposit.
2. Early-stage discussions have been held with existing ceramic and alumina producers in Europe and the
USA with a view to potential synergies.
3. Impact is assembling a marketing team to engage with potential customers further and provide
feedback on the specifications required for end-user products.
Figure 3. The four pieces of the Lake Hope Pre-Feasibility Study Jigsaw Puzzle.
6|Page
ASX ANNOUNCEMENT
Recent ASX releases by Alpha HPA Limited (ASX:A4N), a leader in the HPA industry, show there is significant global
demand for a wide range of HPA products of much more than the 10,000 tonnes per annum Alpha plans to
produce from their full-scale plant to be built over the next two years. Alpha recently received significant funding
of $400 million, a total capex of $500 million, for building this plant from the Australian government. The funding
comprises low-interest loans and demonstrates the ongoing federal (and state) support for critical minerals and
downstream processing, in which Impact intends to participate. The Lake Hope Scoping study had an estimated
capital cost of $250 million (+/- 30%) (ASX Release November 9th 2023).
2.
ARKUN-BEAU-JUMBO Ni-Cu-PGM-REE PROJECT, WA (IPT 100% and 80%)
As highlighted in the previous quarter's report, significant progress was made on the Caligula copper prospect.
However, during this quarter, there has been no major new activity at the Arkun Project.
During the quarter, 413 soil samples previously assayed for ionic leach have been re-assayed to refine drill
target at Beau and Caligula. Of these:
•
•
238 samples from Beau were re-assayed for four acid digest.
175 soils from the northern part of Caligula were submitted for aqua regia digest analysis
Although no additional fieldwork has taken place this quarter, Impact remains committed to advancing the
Arkun Project as soon as the cropping season in the wheatbelt has finalised in December. Preparations are also
underway to finalise land access agreements and necessary statutory approvals ahead of a planned drill
programme in Q1 2025.
Previous geochemical surveys and data from the Mobile Magneto-Telluric (MMT) survey at the Caligula
prospect continue to support a promising outlook for the project. Co funding of up to $180,000 has been
awarded under the WA Government’s EIS Scheme to drill the Caligula copper target.
We remain optimistic about the project's potential and will provide further updates as developments occur.
3. COMMONWEALTH PROJECT (IPT 100%)
During the Quarter, Burrendong Minerals Ltd, who have an option to earn a 75% interest in the Commonwealth
project, made significant strides towards completing its prospectus for an IPO. The prospectus is expected to be
lodged with ASIC early in Q4 CY2024.
OTHER PROJECTS
No significant work was done on Impact’s other projects.
7|Page
ASX ANNOUNCEMENT
4. CORPORATE
Financial Commentary
The Quarterly Cashflow Report (Appendix 5B) for the current period provides an overview of the Company’s
financial activities.
Cash exploration expenditure for the period was $841,000. Corporate and administration expenses amounted
to $592,000. The total amount paid to directors of the entity and their associates in the period (item 6 of
Appendix 5B) was $105,000, including salary, directors’ fees and superannuation.
Cash at September 30th was $1.98 million.
Dr Michael G Jones
Managing Director
Competent Person’s Statement
The review of exploration activities and results contained in this report, except the Lake Hope Project, is based on information compiled by Dr Mike
Jones, a Member of the Australian Institute of Geoscientists. He is a director of the company and works for Impact Minerals Limited. He has sufficient
experience relevant to the style of mineralisation and types of deposits under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
(the JORC Code). Mike Jones has consented to the inclusion in the report of the matters based on his information in the form and context in which it
appears.
The review of exploration activities and results about the Lake Hope Project and the metallurgical test work contained in this report is based on
information compiled by Roland Gotthard, a Member of the Australian Institute of Mining and Metallurgists. He is an employee of Impact Minerals
Limited. He has sufficient experience relevant to the style of mineralisation and types of deposits under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (the JORC Code). Mr Gotthard has consented to the inclusion in the report of the matters based on his information in the
form and context in which it appears.
The data in this report that relates to Mineral Resource Estimates are based on information evaluated by Mr Simon Tear, who is a Member of The
Australasian Institute of Mining and Metallurgy (MAusIMM) and who has sufficient experience relevant to the style of mineralisation and type of
deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the “JORC Code”). Mr Tear is a Director of H&S
Consultants Pty Ltd and consents to the inclusion in the report of the Mineral Resource in the form and context in which they appear.
8|Page
ASX ANNOUNCEMENT
Tenement Information by Listing Rule 5.3.3
Project /
Tenement
Commonwealth
Location
Status
New South
Wales
IPT Interest
at start of
quarter
IPT Interest
at end of
quarter
EL5874
Granted
100%
100%
EL8212
Granted
100%
100%
EL8252
Granted
100%
100%
EL8504
Granted
100%
100%
EL8505
Granted
100%
100%
EL7390
Granted
100%
100%
EL8234
Granted
100%
100%
EL8636
Granted
100%
100%
EL8674
Granted
100%
100%
EL8609
Granted
100%
100%
EL9036
Granted
100%
100%
EL9037
Granted
100%
100%
EL9115
Granted
100%
100%
EL9294
Granted
100%
100%
EL9384
Granted
100%
100%
EL9481
Granted
-
100%
EPM26806
Granted
100%
100%
EPM27571
Granted
100%
100%
EPM27410
Granted
100%
100%
E74/763
Granted
Earning in
-
E74/764
Granted
Earning in
-
E63/2317
Granted
Earning in
-
E63/2318
Granted
Earning in
-
E63/2319
Granted
Earning in
-
E63/2086
Granted
Earning in
-
Broken Hill
Blackridge
Lake Hope
9|Page
New South
Wales
Queensland
Western
Australia
ASX ANNOUNCEMENT
E74/779
Granted
IPT Interest
at start of
Earning
quarterin
E63/2370
Application
Earning in
E70/5424
Granted
100%
100%
E70/5430
Granted
100%
100%
E70/5431
Granted
100%
100%
E70/5432
Granted
100%
100%
E70/5433
Granted
100%
100%
E70/5434
Granted
100%
100%
E70/5490
Granted
100%
100%
E70/5504
Granted
100%
100%
E70/5505
Granted
100%
100%
E70/6598
Granted
100%
100%
E70/6595
Application
-
-
E70/6604
Granted
-
100%
Granted
80%
80%
Granted
80%
80%
Granted
80%
80%
E52/3967
Granted
80%
80%
E52/3985
Granted
80%
80%
Surrendered
100%
0%
Project /
Tenement
Arkun
Doonia
Location
Western
Australia
Western
Australia
E70/5852
Dalgaranga
Western
Australia
E59/2620
Narryer
Gascoyne
E52/4114
10 | P a g e
IPT Interest
at end of
quarter
-
Western
Australia
E15/1790
Jumbo
Status
Western
Australia
Western
Australia
ASX ANNOUNCEMENT
Share your feedback
Discover