Quarterly Activities Report
Released
Released
Announcement PDF
30th JANUARY 2025
CORPORATE ANNOUNCEMENT
DECEMBER 2024 QUARTERLY REPORT
HIGHLIGHTS
1. Lake Hope High Purity Alumina (HPA) Project, WA (IPT earning 80%)
COMPANY DETAILS
Significant progress made on the Pre-Feasibility Study
The Mine at Lake Hope:
A maiden Measured Resource of 730,000 tonnes at 25.8% alumina
(Al₂O₃) defined, underpinning an initial 15-year mine life which is part of
a much larger resources that includes Indicated and Inferred Resources.
Ongoing work towards declaring a maiden Proven Reserve, with mining
and economic studies advancing.
Funding secured to accelerate development of the pilot plant through a
Federal Government grant of $2.87 million in collaboration with CPC
Engineering and Edith Cowan University.
The Process Plant:
CPC Engineering continues engineering studies for the 10,000 tpa HPA
plant, incorporating design improvements for acid regeneration.
Test work progressing, with a 20 kg sample of intermediate material
prepared for acid leaching under the Low-Temperature Leach process.
Product Development and Offtake:
Joseph Casella appointed as Marketing Manager to lead engagement
with potential off-take partners and customers.
Market studies align with strong global demand, positioning Impact for
successful market entry.
2. Arkun-Beau, WA (IPT 100%)
Further landholder liaison has unlocked new areas to sample
311 new soil samples were collected which included infill sampling at
the Caligula target and over new mobile MT anomalies
Drill targeting and planning for Q2 2025
Market Cap: A$33.7m (0.011 p/s)
Issued Capital: 3,059,433,718
ABN 52 119 062 261
9 Richardson Street
West Perth
Western Australia 6005
Phone: +61 (8) 6454 6666
Email:
info@impactminerals.com.au
Website: impactminerals.com.au
DIRECTORS
Mr Peter Unsworth
Chairman
Dr Michael Jones
Managing Director
Mr Paul Ingram
Non-Executive Director
Dr Frank Bierlein
Non-Executive Director
Mr Arron Canicais
Company Secretary
3. Commonwealth Project (IPT 100%)
Burrendong Minerals Limited has released its prospectus for an IPO, offering 25 million shares at
$0.20 per share, with a one-for-two free attaching option exercisable at $0.25 within 36 months.
Impact shareholders have a priority entitlement of $2 million in the IPO.
4. Corporate/Finance
Research and Development Tax Incentive Rebate of $512,000 received during the quarter.
Cash as of December 31st $1.20 million.
2|Page
ASX ANNOUNCEMENT
PROJECT REPORTS
1.
LAKE HOPE HIGH PURITY ALUMINA PROJECT, WA (IPT earning 80%)
During the Quarter, significant progress continued to be made on the Pre-Feasibility Study for the Lake Hope
High Purity Alumina (HPA) Project, located 500 km east of Perth, WA (Figure 1). The PFS has a focus on
achieving 10,000 tonnes per annum (tpa) production of 99.99% (4N) HPA, a critical mineral for high-tech
industries such as lithium-ion batteries, LEDs, and semiconductors.
Figure 1. Location of the Lake Hope Project and proposed haul route to Kwinana.
The Mine at Lake Hope
A maiden Measured Resource of 730,000 tonnes at 25.8% alumina (Al₂O₃) for 189,000 tonnes of contained
alumina was declared during the Quarter (ASX Release 19th November 2024), supporting a planned maiden
Reserve for at least 15-years of production at the target rate of 10,000 tpa HPA. This resource upgrade follows
a program of infill drilling designed to convert Indicated Resources into Measured Resources. It is part of a
much larger resource that includes Indicated and Inferred Resources within a unique deposit of high-grade
alumina hosted in extremely fine-grained evaporite and clay minerals in the top two metres of two small dry
salt lakes in the Lake Hope playa system (ASX Release 21st March 2023).
The larger resource underpins a potentially much longer mine life of at least 25 years, as reported in the
Scoping Study on Lake Hope. The study showed that the project had very robust economics, with an after-tax
Net Present Value (NPV8) of A$1.3 billion and one of the lowest operating costs per tonne of HPA globally (ASX
Release 9th November 2023). Impact confirms that all material assumptions underpinning the production
target and forecast financial information in the Scoping Study continue to apply.
3|Page
ASX ANNOUNCEMENT
Other key developments at the mine include:
The lodgement of the Mining Lease Application (MLA63/684) and associated Miscellaneous Licence
L63/99 (ASX Release 12th August 2024).
A review of mining schedules and logistics planning, with quotes for mining and haulage operations to
Kwinana awaited.
Ongoing discussions with the Ngadju Aboriginal people under a signed Negotiation Protocol aim to
secure Land Access Agreements and Cultural Heritage Management Plans.
Planning of flora, fauna, and heritage surveys for the proposed haul road and other infrastructure is
underway.
The Process Plant at Kwinana
Kwinana has been confirmed as the optimal location for the HPA processing plant due to its strategic
advantages, including proximity to suppliers of chemical reagents required for the processing of Lake Hope
clays and access to buyers for fertiliser and acid by-products, which reduces transport and operating costs.
Engineering Progress
CPC Engineering continued detailed design work for the 10,000 tpa processing plant, including cost estimates
and process flow improvements. Significant focus has been placed on integrating an acid regeneration system,
a critical step to reduce chemical consumption and operational costs. Discussions to secure State Governmentcontrolled land for the plant in Kwinana remain on track.
Test Work and Product Development
Metallurgical test work remains on schedule, with promising results to date. A 20 kg sample of intermediate
material was prepared for advanced acid-leaching trials as part of the Low-Temperature Leach (LTL) Process.
The continued development of fertiliser by-products demonstrates the potential for additional revenue
streams. Bench-scale tests confirm that HPA produced from Lake Hope meets 99.99% purity standards
required for high-tech applications, positioning Impact to deliver a cost-competitive and sustainable product.
Market Strategy and Off-Take
Impact strengthened its commercialisation strategy through the appointment of Joseph Casella as Marketing
Manager (ASX Release 9th October 2024). Joseph, formerly of Tianqi Lithium, brings extensive experience in
critical minerals markets, product development, and international supply chain management. The global HPA
market continues to experience strong demand, growing at a compound annual growth rate (CAGR) of 15% to
20%. Recent market activity highlights robust investor and customer interest, with companies such as Alpha
HPA Limited (ASX:A4N) receiving substantial funding and indicative interest exceeding 30,000 tpa with a
forecast production rate of only 10,000 tpa. Joseph will lead efforts to engage customers, establish off-take
agreements, and refine product specifications to meet market needs.
4|Page
ASX ANNOUNCEMENT
Pilot Plant and CRC-P Grant
A major milestone was achieved with Impact Minerals securing a $2.87 million CRC-P Grant under the Federal
Government’s Cooperative Research Centres Projects (CRC-P) program (ASX Release 22 nd October 2024). The
grant, awarded in collaboration with CPC Engineering and Edith Cowan University (ECU), will fund the
construction of a pilot plant to produce consistent HPA samples for customer qualification trials and off-take
agreements. It will also support the implementation of Membrane Selective Technology (MST), which
enhances reagent regeneration, reduces waste, and aims for “zero-liquid discharge”. This positions Impact to
advance toward a Definitive Feasibility Study (DFS) following the completion of the PFS. CPC Engineering will
design, construct, and manage the pilot plant, leveraging their expertise in HPA processing
Next Steps
Impact remains on track to complete the Pre-Feasibility Study (PFS) for Lake Hope at the end of Q1 2025. Key
deliverables include:
1. Finalised mining schedules and cost estimates.
2. Results from acid regeneration studies and advanced metallurgical testing.
3. Engineering designs and capital cost estimates for the full-scale process plant.
The pilot plant construction, scheduled to begin this quarter, represents a critical step toward commercial
production and customer engagement.
2.
ARKUN-BEAU-JUMBO Ni-Cu-PGM-REE PROJECT, WA (IPT 100% and 80%)
During December 2024, ongoing landholder liaison facilitated access to new target areas within the Arkun
project. During the quarter, 311 soil samples were collected in key target areas. These samples were primarily
collected over Mobile MT anomalies, including targeted infill sampling at the Caligula copper target to refine
drill targets further (Figure 2). In May 2024, Impact was awarded an EIS funding of $180,000 to support drill
testing at Caligula (ASX Release 1 May 2024). The company plans to execute and complete a substantial drill
program in Q2 this year.
About the Recent Soil Geochemistry Survey
A total of 311 soil samples were collected during December 2024. Of these, 197 samples focus on an infill over
the Caligula copper-in-soil and MT anomaly (ASX Release 24 January 2024) at a tighter 50m x 50m spacing, while
97 samples targeted a newly identified deep mobile MT anomaly (Figure 2, 3 and 4). The remaining samples
were collected over additional anomalies, although only partial soil sampling grids could be completed due to
cropping and landholder access constraints. The assays for these soil samples have not yet been received.
5|Page
ASX ANNOUNCEMENT
Figure 2. Magnetic map highlighting Mobile MT anomalies (in red) at the Caligula and New Target showing previous
assayed soil sampling (black points) and new collected soil locations (white points).
In January 2024, Impact delineated a copper-in-soil anomaly extending approximately 5,000 meters northsouth and at least 2,000 meters east-west, remaining open to the east and southwest (Figures 3 and 4). This
anomaly is characterized by elevated levels of copper associated with silver, cobalt, and, in its southern
extent, bismuth, tellurium, and minor molybdenum. This metal assemblage is typical of porphyry copper
deposits, presenting encouraging prospects for future exploration.
Figure 3. Previous soil geochemistry results for copper (Cu)-silver (Ag)-Cobalt (Co)-Bismuth (Bi)-Tellurium (Te)Molybdenum (Mo) in soils at Caligula which have been highlighted in black points in Figure 2.
(ASX Release 24 January 2024).
6|Page
ASX ANNOUNCEMENT
In late 2023, a helicopter-borne MMT survey was conducted to investigate several airborne EM targets. This
survey identified several conductive anomalies coinciding with or near the Caligula copper anomaly,
including an example shown in Figure 4 (ASX Release, 24 January 2024). These conductors may represent
disseminated or massive sulphides.
A notable conductor was also detected a few kilometers east of Caligula, near a major fault identified in
regional airborne magnetic data. This area was included in the recent soil sampling for further evaluation.
Figure 4. A tilted 3D view of an image of the bedrock geology of the Caligula area showing the soil geochemistry anomaly
(coloured squares) and a section line of the MMT data. Purple areas are zones of high conductivity, and two such zones
coincide with the geochemistry. A large conductive anomaly close to a major structure occurs at the eastern end of the
section line. This is a priority area for further exploration.
The identification of the Caligula prospect, with its potential for a significant porphyry copper and/or gold
deposit, represents a critical development at Arkun. The region hosts world-class deposits, including the
Boddington porphyry gold-copper deposit (>25 million oz gold and ~1 million tonnes copper, Newmont Corp)
and the Calingiri porphyry copper-molybdenum deposit (>3 million tonnes copper, ASX: Caravel Minerals
Limited).
Previous re-assays for four acid analysis at Beau in the previous quarter returned similar anomalies determined
by the ionic leach assays (ASX Release 18 August 2022).
7|Page
ASX ANNOUNCEMENT
3.
COMMONWEALTH PROJECT (IPT 100%)
During the Quarter, significant progress was made regarding the Commonwealth Project in New South Wales,
with the advancement of an Initial Public Offering (IPO) by Burrendong Minerals Limited, an unrelated public
company set to take ownership of a majority interest in the project (ASX Release 21 st November 2024).
Burrendong Minerals IPO – Unlocking Value
Burrendong Minerals Limited released its prospectus for an IPO, offering 25 million shares at $0.20 per share,
with a one-for-two free attaching option exercisable at $0.25 within 36 months. Impact shareholders have a
priority entitlement of $2 million in the IPO. Upon successful listing, Impact will receive a $275,000 cash
payment, a 12.5% shareholding in Burrendong, making Impact its largest shareholder, and retain of a 49%
interest in the Commonwealth Project. Burrendong has the option to acquire an additional 24% interest by
investing $5 million over the next three years. This agreement positions Impact Minerals to retain significant
exposure to the Commonwealth Project while focusing on its flagship Lake Hope HPA Project.
All shareholders and other interested parties of interest are encouraged to review the prospectus which can be
found at:
https://impactminerals.com.au/burrendong-priority-offer
https://www.burrendongminerals.com.au
Project Overview and Exploration Upside
The Commonwealth Project, located in the Lachlan Fold Belt—home to world-class deposits like Cadia-Ridgeway
and recent discoveries such as Boda-Kaiser—covers a 675 km² tenement package. Burrendong will initially focus
on extending and expanding known resources through an aggressive drill program of up to 5,000 metres of
diamond and RC drilling once listed.
Burrendong has three JORC-compliant Resources include:
1. Commonwealth Mine (Main Shaft and Commonwealth South)
2. Silica Hill
3. Galwadgere
Key target areas include:
1. Commonwealth Mine:
Extensions at Main Shaft, where high-grade massive sulphide mineralisation remains open at depth and
along trend (ASX Release 26 th November 2024).
Significant drill intercepts to be followed up include:
8|Page
o
5.7 m at 3.8 g/t gold, 347 g/t silver, 10.8% zinc, and 3.7% lead.
o
8.1 m at 6.0 g/t gold, 193 g/t silver, 5.9% zinc, and 2.3% lead.
ASX ANNOUNCEMENT
2. Silica Hill:
Follow-up drilling at this virgin discovery to target extensions of bonanza-grade silver and gold veins.
Exceptional previous results include (ASX Release 26th November 2024):
o
22.5 m at 1.7 g/t gold and 276 g/t silver, including 0.3 m at 4,200 g/t silver.
o
21.8 m at 0.6 g/t gold and 273 g/t silver, with intervals up to 6,240 g/t silver.
3. Galwadgere:
A copper-gold resource located 10 km south of Commonwealth, with historical intercepts of:
o
53 m at 0.55% copper and 0.75 g/t gold, including 6 m at 1.0% copper.
Strategic Potential and Geological Significance
The Commonwealth Project demonstrates strong geological similarities to the Eskay Creek Deposit in Canada’s
renowned Golden Triangle, one of the world’s premier high-grade VMS (volcanogenic massive sulphide)
deposits. Both projects are characterised by high-grade gold and exceptionally high-grade silver veins, as well as
the same sulphide mineral assemblage, including gold, silver sulphosalts, zinc, lead, and barite. The Main Shaft
and Silica Hill prospects remain underexplored, with the potential to discover further massive sulphide lenses.
Historical drilling has identified zones of exceptional silver grades, including up to 6,240 g/t silver (200 oz/t) over
narrow intervals (ASX Release 26th November 2024).
Next Steps
With a fully funded drill program on listing and a focus on extending known high-grade resources, Burrendong
Minerals is poised to unlock the significant exploration upside at the Commonwealth Project. Impact Minerals
will continue to benefit through its retained equity and interest in the project.
4.
OTHER PROJECTS
No significant work was done on Impact’s other projects.
5.
CORPORATE
Financial Commentary
During the Quarter Impact Minerals Limited (ASX:IPT) announced that it had received a rebate of $512,000
before costs from the Research and Development Tax Incentive scheme for the financial year ending June
2024 (ASX Release 20th November 2024).
These funds will be used to continue the Pre-Feasibility Study on Impact’s flagship Lake Hope High Purity Alumina
(HPA) Project, which is scheduled for completion in Q1 2025. They will also contribute to the accelerated start of
the recently announced research and development project in conjunction with CPC Engineering and Edith Cowan
University to help build a pilot plant for the Lake Hope Project. The project will also be funded by the recently
announced grant of $2.87 million under the Federal Government’s CRC-P programme (ASX Releases October
22nd, 2024, and November 18th, 2024).
9|Page
ASX ANNOUNCEMENT
The Quarterly Cashflow Report (Appendix 5B) for the current period provides an overview of the Company’s
financial activities.
Cash exploration expenditure for the period was $893,000. Corporate and administration expenses amounted
to $477,000. The total amount paid to directors of the entity and their associates in the period (item 6 of
Appendix 5B) was $118,000, including salary, directors’ fees and superannuation.
Cash at December 31st was $1.20 million.
Dr Michael G Jones
Managing Director
Competent Person’s Statement
The review of exploration activities and results contained in this report, except the Lake Hope Project, is based on information compiled by Dr Mike
Jones, a Member of the Australian Institute of Geoscientists. He is a director of the company and works for Impact Minerals Limited. He has sufficient
experience relevant to the style of mineralisation and types of deposits under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
(the JORC Code). Mike Jones has consented to the inclusion in the report of the matters based on his information in the form and context in which it
appears.
The review of exploration activities and results about the Lake Hope Project and the metallurgical test work contained in this report is based on
information compiled by Roland Gotthard, a Member of the Australian Institute of Mining and Metallurgists. He is an consultant to Impact Minerals
Limited. He has sufficient experience relevant to the style of mineralisation and types of deposits under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (the JORC Code). Mr Gotthard has consented to the inclusion in the report of the matters based on his information in the
form and context in which it appears.
The data in this report that relates to Mineral Resource Estimates are based on information evaluated by Mr Simon Tear, who is a Member of The
Australasian Institute of Mining and Metallurgy (MAusIMM) and who has sufficient experience relevant to the style of mineralisation and type of
deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the “JORC Code”). Mr Tear is a Director of H&S
Consultants Pty Ltd and consents to the inclusion in the report of the Mineral Resource in the form and context in which they appear.
Impact confirms that it is not aware of any new information or data that materially affects the information included in this market announcement and,
in the case of estimates of mineral resources or reserves, that all material assumptions and technical parameters underpinning the estimates in this
market announcement continue to apply and have not materially changed.
10 | P a g e
ASX ANNOUNCEMENT
Tenement Information by Listing Rule 5.3.3
Project /
Tenement
Commonwealth
Location
Status
New South
Wales
IPT Interest
at start of
quarter
IPT Interest
at end of
quarter
EL5874
Granted
100%
100%
EL8212
Granted
100%
100%
EL8252
Granted
100%
100%
EL8504
Granted
100%
100%
EL8505
Granted
100%
100%
EL7390
Granted
100%
100%
EL8234
Granted
100%
100%
EL8636
Granted
100%
100%
EL8674
Granted
100%
100%
EL8609
Granted
100%
100%
EL9036
Granted
100%
100%
EL9037
Granted
100%
100%
EL9115
Granted
100%
100%
EL9294
Granted
100%
100%
EL9384
Granted
100%
100%
EL9481
Surrendered
100%
-
EPM26806
Granted
100%
100%
EPM27571
Granted
100%
100%
EPM27410
Granted
100%
100%
E74/763
Granted
Earning in
-
E63/2318
Granted
Earning in
-
E63/2319
Granted
Earning in
-
E63/2086
Granted
Earning in
-
M63/684
Application
Earning in
-
L63/99
Application
Earning in
-
E74/779
Granted
Earning in
-
E63/2370
Granted
Earning in
E63/2257
Granted
Earning in
Broken Hill
Blackridge
Lake Hope
11 | P a g e
New South
Wales
Queensland
Western
Australia
ASX ANNOUNCEMENT
E63/2492
Granted
IPT Interest
at start of
Earning
quarterin
E63/2493
Granted
Earning in
E63/2504
Application
Earning in
E63/2505
Application
Earning in
E63/2506
Application
Earning in
E63/2507
Application
Earning in
E70/5424
Granted
100%
100%
E70/5430
Granted
100%
100%
E70/5431
Granted
100%
100%
E70/5432
Granted
100%
100%
E70/5433
Granted
100%
100%
E70/5434
Granted
100%
100%
E70/5490
Granted
100%
100%
E70/5504
Granted
100%
100%
E70/5505
Granted
100%
100%
E70/6598
Granted
100%
100%
E70/6595
Application
-
-
E70/6604
Granted
100%
100%
Granted
80%
80%
Granted
80%
80%
Granted
80%
80%
E52/3967
Granted
80%
80%
E52/3985
Granted
80%
80%
Project /
Tenement
Arkun
Doonia
Location
Western
Australia
Western
Australia
E70/5852
Dalgaranga
Western
Australia
E59/2620
Narryer
12 | P a g e
IPT Interest
at end of
quarter
Western
Australia
E15/1790
Jumbo
Status
Western
Australia
ASX ANNOUNCEMENT
Share your feedback
Discover